Plan of Activities

Neighbourhood Plan Timeline Oct 2015

Upper Beeding Master Project Plan Feb 2015

Draft Plan UB Neighbourhood Plan 2013 V4

Start/Prep

  • Clarify why a plan is needed.                                                             May 2013 COMPLETED
  • Publicise the intention to produce a plan.                                      June 2013 COMPLETED
  • Identify and contact key local partners.                                            July 2013 STARTED
  • Dialogue with the local planning authority.                                     July 2013 STARTED
  • Produce a project plan with costings.                                              July 2013 STARTED

Neighbourhood Area

  • Determine the neighbourhood area.                                             July 2013 COMPLETED
  • Submit neighbourhood area proposal.                                         22/08/2013 COMPLETED
  • Notice of Consultation                                                                       09/09/13 – 21/10/13
  • Horsham & SDNP LPA approval                                          01/11/2013 ACTUAL 16/12/13

Neighbourhood Plan Team (managed though PC) 

  • Identify & pull together Team                                                          Aug. 2013 COMPLETED
  • Hold Initial Team Meeting                                                               11/09/2013 COMPLETED
  • Identify Roles & Requirements of the Team                               11/09/2013 COMPLETED
  • Produce Draft Questionnaire                                                          21/09/2013 COMPLETED
  • Feedback on Draft Questionnaire                                                 28/09/2013 COMPLETED
  • Agree Final Questionnaire                                                              09/10/2013 COMPLETED
  • Submit ideas for Vision Statement                                                21/09/2013 COMPLETED
  • Feedback on Vision Statement                                                      28/09/2013 COMPLETED
  • Agree Vision Statement                                                                   09/10/2013 COMPLETED
  • Submit ideas on groups in Village                                                21/09/2013 COMPLETED
  • Feedback on Groups & Team Ownership                                   28/11/2013 COMPLETED
  • Agree Groups & Team Owner                                                        09/01/2014 COMPLETED

Community Engagement & Involvement  STARTED – COMPLETE BY OCT.2014

  • Publicity.
  • Engage local partners.
  • Initial community engagement (broad issues).
  • Provide feedback.

Building the Evidence Base

  • Review existing evidence.
  • Identify gaps in evidence.
  • Compile new evidence.
  • Analysis of evidence.

Themes, Aims, Vision, Options                                            To Be Expanded/Developed

  • Identify key issues and themes.
  • Prioritise issues and themes.
  • Develop key aims.
  • Lo 

Writing the Plan

  • Policies, proposals, site allocations.
  • Consider sustainability, diversity, equality, delivery.

 

Consultation

  • Consultation on plan. * (Min 4 weeks)
  • Amend plan.

 Submission

  • Submit to LPA.                                                                                             By  JAN.  2015
  • LPA publicises. * (Min 4 weeks)

Independent Examination

  • LPA appoints examiner.
  • Examination takes place.
  • Examiner’s Report.                                                                                        By March 2015

Referendum

  • Publicise referendum. ** (Min 6 weeks)
  • Referendum. /            The Plan is Completed                                            By May 2015